An abrasive import lead time is not one number, it is four: the production window, the ocean transit to the port, the customs clearance, and the inland leg to the plant. The program is planned around the sum of the four, and the window moves with the lane conditions, not with a fixed calendar. This page is the FAQ that breaks the lead time into the four pieces, and the planning rule that keeps a program from stalling on the window.

The lead time, in four pieces
  1. Production — the window the lot is built, from spec to pack
  2. Ocean transit — the lane to the port, the West Coast shorter than the East
  3. Customs — the clearance at the port, on the documents the lot carries
  4. Inland leg — the truck or rail from the port to the plant

The four pieces, and which one the program controls

The four pieces are the production, the ocean, the customs, and the inland leg, and the program controls the first and the last. The production window is set by the spec and the pack, and the OEM and shipping page describes the production and the pack stages. The ocean transit is the lane, and the lane is set by the destination, with the regional guides carrying the lane detail for each region. The customs is on the documents the lot carries, and the customs clearance article is the step the lot clears on. The inland leg is the truck or rail, and it is the piece the program controls on its side. The four are the window, and the program is planned around the sum.

The window moves, so the plan is the confirmation, not the number

The ocean window moves with the lane conditions, and the plan is the confirmation of the window per program in the quote, not a fixed number. A program that plans on a fixed number is the one that stalls when the lane moves, and the confirmation is what the program runs on. The shipping and OEM page is where the window is confirmed, and the quality process covers the lot that the window is for. The rule is to confirm the window per program, because the window is the plan, and the fixed number is the stall.

Air freight is the exception, not the program

The air window is three to seven days, and it is the fast option for a sample or a critical hold-up, where the ocean window is too long. It is not the scheduled program, because the cost is the multiple of the ocean and the program is built on the scheduled supply. The lead-time FAQ covers the terms the air and the ocean run under, and the shipping page is where the air is flagged for the urgent item. The air is the exception, and the scheduled supply is the program, and the window is what the program is built on.

Send the destination and the timing to the order

Send the destination and the timing you need to the quote request; the team confirms the current window for the lane and the pack that gets it there. The regional guides carry the lane detail, and the technical specs page has the product reference the window is for. The four pieces are the window, the confirmation is the plan, and the scheduled supply is the program that runs on it, and the destination and the timing are what the window is confirmed against.